What is Earned Value Management (EVM) ?
- Oscar Conti
- Mar 29
- 2 min read

Earned Value Management (EVM) is a project management technique used to measure project performance by integrating scope, schedule, and cost. It provides a clear, data-driven way to assess how much work has been completed, how much was planned, and how much it actually cost, helping project teams and stakeholders identify variances early and make informed decisions.
Earned Value Management (EVM) is widely used by the U.S. government and major construction firms to control project cost, schedule, and scope. CONTIDB supports this need by offering certified EVM experts who help clients implement and optimize performance management strategies.
Main Components of EVM
Planned Value (PV)
Budgeted cost of scheduled work at a given point in time.
Formula: PV = Planned % Complete × Budget at Completion (BAC)
Earned Value (EV)
Budgeted value of the actual work completed.
Formula: EV = Actual % Complete × BAC
Actual Cost (AC)
Total cost incurred for work performed so far.
The Earned Value chart
EVM Key Values and Definitions
BAC: Total approved project budget
PV: Budgeted value of scheduled work
EV: Budgeted value of completed work
AC: Actual cost spent to date
Performance Metrics and Forecasts
Cost Variance (CV): EV – AC
Positive = under budget
Negative = over budget
Schedule Variance (SV): EV – PV
Positive = ahead of schedule
Negative = behind schedule
Cost Performance Index (CPI): EV ÷ AC
1 = on budget
<1 = over budget
Schedule Performance Index (SPI): EV ÷ PV
1 = on schedule
<1 = behind schedule
Estimate at Completion (EAC):
EAC = BAC ÷ CPI
EAC = AC + (BAC – EV) ÷ CPI
EAC = AC + (BAC – EV)
Estimate to Complete (ETC):
ETC = EAC – AC
ETC = (BAC – EV) ÷ CPI
Variance at Completion (VAC): BAC – EAC
Positive = under budget
Negative = projected overrun
Worked Example
Scenario:Project duration = 12 monthsTotal budget = $12MAfter 3 months:
10% of work completed
$2.5M spent
Calculations:
PV = $12M × (3 ÷ 12) = $3M
EV = $12M × 10% = $1.2M
AC = $2.5M
Performance:
CV = EV – AC = 1.2M – 2.5M = –$1.3M
CV% = –108%
SV = EV – PV = 1.2M – 3M = –$1.8M
SV% = –60%
CPI = 1.2 ÷ 2.5 = 0.48
SPI = 1.2 ÷ 3 = 0.4
Forecasts:
EAC = 12 ÷ 0.48 = $25M
ETC = (12 – 1.2) ÷ 0.48 = $22.5M
Time to Complete = (12 – 1.2) ÷ 0.4 = 27 months
Total Project Duration = 3 + 27 = 30 months
Conclusion:Without corrective action, the project will take 2.5 times longer and cost more than double the original budget.
Becoming an EVM Expert
To specialize in EVM, professionals often pursue certifications from AACE International. The Earned Value Professional (EVP) is the leading credential focused on EVM. Other relevant certifications include the Certified Cost Professional (CCP) and Planning & Scheduling Professional (PSP). These require education, project experience, and passing an exam. Beyond certification, real expertise comes from applying EVM on complex projects and using tools like Primavera P6, Microsoft Project, and Deltek Cobra.
Comments